Title and
Construction
Updates

Page Last Updated February 2019

Welcome to the Exford Waters Title Updates Page.

We are committed to ensuring purchasers have access to their lots as soon as possible. Delays may occur due to unforeseen weather conditions or construction setbacks. We encourage buyers to check this page for any updates along the way.

If you have any additional questions regarding settlements please call the Sales Office on 1800 777 800 or email exfordwaters@rpmrealestate.com.au.

Anticipated Title Dates
Stage 1right arrow                   Titled
 
Stage 2right arrow                  Titled
 
Stage 3right arrow                  Titled
 
Stage 7right arrowPhase 7Completetion & inspection of Works
March 2019
Stage 5right arrowPhase 5Electrical & Telecommunication
2nd Quarter 2019
Stage6 right arrowPhase 5Electrical & Telecommunication
2nd Quarter 2019
Stage 8right arrowPhase 4Road Boxing, Kerb & Channel
3rd Quarter 2019

Page Last Updated February 2019

Phase 1 image
Phase 1:
Council and authority acceptance of documentation including engineering design to allow physical works to commence on site.
Phase 2 image
Phase 2:
Preparation of the site to achieve design lot levels including site scrape, shaping of the existing ground and construction of retaining walls if required.
Phase 3 image
Phase 3:
Installation of sewer and drainage to service the development stage.
Phase 4 image
Phase 4:
Prepare the ground and start to construct the lower layers of the road pavement. Install water and gas mains and construct kerb and channel.
Phase 5 image
Phase 5:
Trench and install electrical and telecommunication services once kerb and channel works are complete.
Phase 6 image
Phase 6:
Prepare the ground in readiness to construct footpaths. Construct footpaths and topsoil nature strips. Construction of middle pavement layers and placement of asphalt.
Phase 7 image
Phase 7:
Council and Service Authority works inspections and sign-off to constructed works including roads and services. Provision of final documentation to Council to facilitate a Statement of Compliance for the development stage.
Phase 8 image
Phase 8:
Registration of individual lots from each stage occurs at the Titles Office and your block is now ready for you to settle and start the construction of your new home. Congratulations!